Completed: Jan 1, 2021
Ewart Hill Reservoir No. 2 Improvements
Milestone timeline:
Planning
Summer 2020
Design
Completed: Sep 1, 2021
Summer 2021
Bid
Completed: Dec 2, 2021
Fall 2021
Construction
Completed: Jun 13, 2022
Summer 2022
Originally constructed in 1954, the Ewart Hill Reservoir No. 2 is a 5 million gallon covered concrete basin that makes up approximately 30% of the utility's total finished water storage. The improvements consists of installation of a flexible membrane liner to prolong the service life of the existing reservoir and improve water utility system operations and maintenance.