Water Treatment Facility Filter Expansion

Milestone timeline:

Planning
Completed: May 31, 2023
Early 2023
Design Permitting
Completed: Aug 31, 2024
Summer 2024
Bidding
Completed: Oct 31, 2024
Fall 2024
Construction
Late 2025

The City's water treatment facility (WTF) was originally constructed in 1963 with several upgrades since that time. The WTF has a current capacity of 12.0 million gallons per day (mgd) with conventional water treatment process including 5-sedimentation basins, 4-multimedia gravity filters, chlorination, fluoridation and corrosion control.

The project generally consists of installation of additional multimedia gravity filters and associated piping, instrumentation, and appurtenances, which will increase the facility’s permitted capacity to 15-mgd.

Devin Owen, Utilities Engineer

Adam Steurer PE, Utilities Director

Ricky Levi, Water Treatment Manager