7th Avenue Streetscape

Milestone timeline:

Kickoff Public Meeting
Completed: Nov 8, 2018
November 2018
Received Green Stormwater Improvement Grant (NC Dept. of Environmental Quality) 319 Grant
Completed: Dec 5, 2019
December 2019
Streetscape Design
Completed: Jan 31, 2022
2020
Open House Public Input Meeting
Completed: Feb 13, 2020
February 2020
Underground Utility Design
Completed: Dec 31, 2021
2021
1st Solicitation of Bids
Completed: Aug 1, 2021
August 2021
2nd Solicitation of Bids
Completed: Dec 31, 2021
October 2021
CMAR Solicitation & Selection
Completed: Oct 31, 2022
2022
Opening of Bids
Completed: Dec 7, 2023
November/December 2023
Contract Awarded to Harper General Contractors
Completed: Dec 14, 2023
December 2023
Informational Meeting
Completed: Jan 18, 2024
January 18, 2024
Construction Start/Street Closure
Completed: Jan 29, 2024
Week of January 29, 2024
MLK / Grove Intersection Closure
Completed: May 7, 2024
May 7, 2024
Maple Street Intersection Closure
TBD

The Seventh Avenue Streetscape Project is an investment in pedestrian, water, sewer and stormwater infrastructure, lighting and landscaping in the business district. It aims to improve walkability, improve connections to the Main Street Municipal Service District, and highlight the character of the historic district. Slated to begin construction in early 2024, the project area includes part of the intersection at 7th Avenue and Grove Street, 7th Avenue from the intersection to Maple Street, as well as a portion of Locust Street. 

City Council authorized a contract with Harper General Contractors to lead the project in December 2023.  

 Business shopping map

Use the 7th Avenue Streetscape Progress Viewer to compare drone photos of project progress and plan overlays.

drone photo of 7th avenue construction

To receive 7th Avenue Streetscape Alerts, opt-in for 'Downtown Alerts' via Hendersonville's AlertHVL Notification System.

Sign up for alerts

 

Brendan Shanahan

City Engineer

bshanahan@hvlnc.gov

(828) 233-3237

Documents

Streetscape Design
7th Avenue Streetscape Final Designs
Streetscape Design
7th Avenue Streetscape Meeting Flyer
Streetscape Design
City Council Presentation - December 7, 2023
Streetscape Design
Presentation of design concept for 7th Avenue Streetscape
Project Updates: 
June 28 Update
Friday, June 28, 2024
Recent Work Completed:
  • Water connections were completed at N Grove in the last 2 weeks.  Final concrete was placed last Friday at N Grove intersection.
  • Street trees, lighting and underground conduit has been installed along north side.  Some utilities were transferred from the old polls to the new ones.
  • Contractor has worked to install electric conduit for lighting.  
  • Paving has been completed in the N Grove intersection.
  • Brick pavers have been placed in crosswalks at N Grove intersection.
  • Curb and gutter has been installed along the east side of Locust street intersection.
Upcoming work:  
  • Contractor will continue to complete work to fully open the N Grove intersection, this work includes:
    • completing the new sign
    • landscaping
    • striping
    • final punch-list items  
  • The primary focus of concrete work will be moving to the south side of the street soon.  
  • Unfortunately, the ATT lines have not been moved to the new poles, therefore the old poles remain in place and will begin hindering the ability to efficiently perform the necessary work.  
  • The contractor is working to find ways to work between the poles, while minimizing interference with demolition and utility crews.  
Schedule and Updates: It is expected that the Grove intersection work will be completed by the mid-July date previously indicated.  Shortly after opening N Grove intersection the Maple St. intersection will be closed for utility installation.
 
Progress photos:
7th Avenue Streetscape Work
 
7th Avenue Streetscape Work
7th Avenue Streetscape Work
 
June 14 Project Updates
Friday, June 14, 2024

Project Updates

Work completed in last 2 weeks: 

  • Post construction verifications have been completed on waterlines.  Engineering is working to complete final paperwork to certify the new lines for service. 
  • Concrete work has been focused on MLK intersection with most of the concrete curb and gutter completed.   
  • Street trees, up lighting, and decorative light poles have been installed on the north side from Locust to N. Grove. 
  • Bio-retention cells have been completed along the same section.   

Schedule and updates: 

City staff from Engineering, Downtown, and Administration have been working closely with project leadership at Harper General Contractors on scheduling closures and working toward a shared goal of project completion in a timely manner. City staff have been working with Harper to coordinate the project schedule in ways that don’t have a negative impact on the overall completion timeline.  

City staff will be providing weekly project updates and share the timing of future significant impacts as information is available. Members of Harper’s team will continue to coordinate sidewalk and other access impacts to individual businesses as the project progresses.  

Even though additional portions of sidewalks are being completed, the project area is still an active construction site, and we will continue to prioritize safety regarding pedestrian access. 

Updates on Closures: 

  • The Grove Street intersection is expected to reopen in mid-July.  
  • The Maple Street Intersection will close AFTER the completion of the Grove intersection. This will allow the construction team to focus resources on completing infrastructure tie-ins and reopening the Grove intersection before closing the Maple intersection, which will also facilitate a less complicated detour and improved access points to businesses.