7th Avenue Streetscape
Milestone timeline:
The Seventh Avenue Streetscape Project is an investment in pedestrian, water, sewer and stormwater infrastructure, lighting and landscaping in the business district. It aims to improve walkability, improve connections to the Main Street Municipal Service District, and highlight the character of the historic district. Slated to begin construction in early 2024, the project area includes part of the intersection at 7th Avenue and Grove Street, 7th Avenue from the intersection to Maple Street, as well as a portion of Locust Street.
City Council authorized a contract with Harper General Contractors to lead the project in December 2023.
To receive 7th Avenue Streetscape Alerts, opt-in for 'Downtown Alerts' via Hendersonville's AlertHVL Notification System.
Documents
- Water connections were completed at N Grove in the last 2 weeks. Final concrete was placed last Friday at N Grove intersection.
- Street trees, lighting and underground conduit has been installed along north side. Some utilities were transferred from the old polls to the new ones.
- Contractor has worked to install electric conduit for lighting.
- Paving has been completed in the N Grove intersection.
- Brick pavers have been placed in crosswalks at N Grove intersection.
- Curb and gutter has been installed along the east side of Locust street intersection.
- Contractor will continue to complete work to fully open the N Grove intersection, this work includes:
- completing the new sign
- landscaping
- striping
- final punch-list items
- The primary focus of concrete work will be moving to the south side of the street soon.
- Unfortunately, the ATT lines have not been moved to the new poles, therefore the old poles remain in place and will begin hindering the ability to efficiently perform the necessary work.
- The contractor is working to find ways to work between the poles, while minimizing interference with demolition and utility crews.
Project Updates
Work completed in last 2 weeks:
- Post construction verifications have been completed on waterlines. Engineering is working to complete final paperwork to certify the new lines for service.
- Concrete work has been focused on MLK intersection with most of the concrete curb and gutter completed.
- Street trees, up lighting, and decorative light poles have been installed on the north side from Locust to N. Grove.
- Bio-retention cells have been completed along the same section.
Schedule and updates:
City staff from Engineering, Downtown, and Administration have been working closely with project leadership at Harper General Contractors on scheduling closures and working toward a shared goal of project completion in a timely manner. City staff have been working with Harper to coordinate the project schedule in ways that don’t have a negative impact on the overall completion timeline.
City staff will be providing weekly project updates and share the timing of future significant impacts as information is available. Members of Harper’s team will continue to coordinate sidewalk and other access impacts to individual businesses as the project progresses.
Even though additional portions of sidewalks are being completed, the project area is still an active construction site, and we will continue to prioritize safety regarding pedestrian access.
Updates on Closures:
- The Grove Street intersection is expected to reopen in mid-July.
- The Maple Street Intersection will close AFTER the completion of the Grove intersection. This will allow the construction team to focus resources on completing infrastructure tie-ins and reopening the Grove intersection before closing the Maple intersection, which will also facilitate a less complicated detour and improved access points to businesses.