Parking Garage

Milestone timeline:

  1. June 2020
    Schematic Design Review at 3 stories (4 levels)
    Completed: Jun 4, 2020
  2. October 2020
    Site Plan Approved
    Completed: Oct 1, 2020
  3. July 2021
    Finalized Design & Permitting
    Completed: Jul 1, 2021
  4. September 2021
    Start of Demolition of Existing Buildings
    Completed: Sep 7, 2021

Project Updates: 
Downtown Parking Background & Updates

 

In 2022, the Downtown Parking Garage at the corner of 5th Avenue and Church Street is under construction. Concurrently with the garage, a comprehensive parking management update will address demand for on-street parking and off-street, permitted parking. A 3-story (4-level) garage is underway at the corner of 5th Avenue and Church Street.

Learn more about Parking Downtown

View the Downtown Parking Garage StoryMap

Join City Council at the Parking Deck Grand Opening on March 1, 2023 at 1:00 PM. View ceremony details on the event calendar.

parking deck rendering 2021

Architect

Walker Consultants

Construction Manager at Risk

Edifice General Contractors

Map of construction site