Completed: Jun 4, 2020
Parking Garage
Milestone timeline:
- June 2020Schematic Design Review at 3 stories (4 levels)Completed: Jun 4, 2020
- October 2020Site Plan ApprovedCompleted: Oct 1, 2020
- July 2021Finalized Design & PermittingCompleted: Jul 1, 2021
- September 2021Start of Demolition of Existing BuildingsCompleted: Sep 7, 2021
Project Updates:
Downtown Parking Background & Updates
In 2022, the Downtown Parking Garage at the corner of 5th Avenue and Church Street is under construction. Concurrently with the garage, a comprehensive parking management update will address demand for on-street parking and off-street, permitted parking. A 3-story (4-level) garage is underway at the corner of 5th Avenue and Church Street.
Architect
Walker Consultants
Construction Manager at Risk
Edifice General Contractors